Team removed 120k lbs. of metal/old equipment. 40k lbs. were for RPS and 80k lbs. were for WHP and approved to be dispositioned with Jerry Gushrowski. The recovered cost estimate is as follows : 40k lbs. = 20 tons x $200/ton = $4,000) We should see the recovery in November. I will follow up and advise Finance.
This project of cleaning exterior RCVG started in July of 2025 with a submission request to WHP Clyde to dispose of equipment in September 2025. Approval form WHP came in October of 2026 (13 months later), and we moved quickly to purge the area. This will facilitate RPS and provide us a staging area for up-and-coming disposition as we continue to improve the facility. I will work diligently to have items removed timely and receive the appropriate costs.
Great project to finally stamp closed! Diligence pays off!
This is savings is a one-time savings which will be realized in NOV 2026.